Budget problems cast shadow over Poznan's Lawica airport development
A new terminal will open to passengers on Sunday at Poznan's Lawica airport,
even though financial problems mean the full investment may not be
completed. An estimated zl.67 million has been spent on the project to date.
But among the work still to be completed is the construction of a parking
apron for planes. The first stage, costing around zl.15 million, is due to
be completed in three weeks. The second stage envisages extending the apron
to the terminal. However, according to Lawica airport general manager
Krzysztof Pawlowski, the full investment may not be completed, since the
budget shortfall is too great. The airport has already received zl.3 million
of State funding to finance its development. (Puls Biznesu, p. 13) A.Z.