Facelift for Warsaw's Krakowskie Przedmiescie

The second stage of the tender has begun and now in a about a week's time the companies which made it past the first round have to declare at what cost they can rebuild the street. However, should they have any doubts and questions referring to the tender, the whole procedure might be prolonged by up to six weeks. Miroslaw Kochalski, acting Mayor of Warsaw, believes that construction works will start in June. The cracked pavement will be replaced by granite paving. The works will last 15 months. Warsaw authorities hope to receive zl.17.3 million EU funding for the project. (WBJ Real Estate Newsletter)