H. Cegielski's euro 200 million Sudan contract still awaits investment guarantees
H. Cegielski-Poznan is still awaiting final confirmation before going ahead
with the largest contract in its history. The contract, with an estimated
value of euro 200 million, relates to the construction of a power plant in
Khartoum in Sudan. Construction work, which is due to start this year, will
be undertaken by H. Cegielski in partnership with Siemens Industrial S
olutions and Services Group. Siemens will provide the electrical systems and
the Polish company, which could be entitled to as much as half the con
tract's value, will be responsible for the mechanical equipment. "The
contract was signed at the end of October 2001. It's what is known as a high
risk contract. Its realization is dependent on an advanced payment to the
contractors," explained Boleslaw Januszkiewicz, spokesperson for H. Ce
gielski. He added that the Sudanese side is still trying to obtain the bank
guarantees necessary to begin the project, which is scheduled for completion
in 2004. (Prawo i Gospodarka, p. 4) A.Z.