Huta Katowice to restart production at Baildon mill
Huta Katowice (HK) steelworks wants to restart production at a rolling mill
in Huta Baildon, a steelworks that had gone into receivership. They want
first to rent out the installation in Baildon and then to buy it. They are
not going to do so directly, but rather create a company that would probably
be called PHS Baildon. HK is now trying to organize some financing, and will
probably take a loan for the investment, Andrzej Capiga, deputy chairman of
HK told Puls Biznesu. He did not want to say, however, how much HK might
offer for the rolling mill, though the value of Baildon had previously been
assessed at zl. 230 million. Restarting production in the rolling mill could
be a good solution for HK as it is presently using only 50% of its
production capacity for finished products, while the production of
semi-products is unviable and Baildon could produce iron for construction.
Thanks to the investment at least 100 workers could go back to work in
Baildon. (Puls Biznesu, p. 4) A.D.