PGE wants to start tender procedures for offshore wind farm projects in the second quarter, according to Krzysztof Fuzowski, vice-president of PGE Baltica.
"The construction schedule for our wind farms is extremely tight. We want to make the final investment decision in 2023, and until then we will conduct several major tenders, including tenders for the main components: turbines, substations, foundations, cables. We intend to start the tender procedures in the second quarter of this year and finish them in 2022". - Vice President Fuzowski said during the offshore opinion market conference.