Skip to content
Advertisement

Business

PGE’s Turów unit construction launched

16:13

Poland’s largest energy group PGE has issued a notice to proceed for the contractors of the new power generation unit in the Elektrownia Turów power plant, the company said in a press release on Monday. The consortium responsible for the construction consists of Mitsubishi Hitachi Power Systems Europe GmbH (55.38 percent) and Budimex. The facility is due to be completed within 56 months from the notice, in the third quarter of 2019. The value of the investment is PLN 4 billion.

More from Business All