Compensation due if Yamal gas pipeline is not built
In the event that the second Yamal gas pipeline from Russia to Germany via
Poland is not constructed, the Bartimpex company owned by Aleksander
Gudzowaty, the main contractor of the planned investment, will earn $150
million in compensation, claims Gazeta Wyborcza. Construction of the
pipeline was assumed in the Polish-Russian agreement of August 1993. In the
protocol signed in February 1995 by the Democratic Left Alliance (SLD) -
Polish Peasants Party (PSL) coalition with the Russian government,
construction of the pipeline should have started in 1998 and ended this
year. According to Gazeta Wyborcza, on July 27, 2000, annex no 13 to the
earlier agreement between Bartimpex with EuRoPol Gaz, the Polish-Russian
company responsible for construction and utilizing the Polish part of the
pipeline, was signed. In case of a breach of the agreement, 15 percent of
the investment value, estimated at $150 million, would be awarded as
compensation to a party that did not breach the agreement. However the
construction has not started so far. After no compromise between Poland and
Russia on the route of the pipeline, it is unclear when or even if the
construction will start at all. (Gazeta Wyborcza, pp.1, 23), M.T.