The authorities in the Gmina Centrum district of Warsaw have signed an agreement on the construction of feeder roads for the Siekierkowski Bridge. The contract, valued at euro 124.5 million, is for 3.7 kilometers of access roads on the left bank of the Wisla. A consortium of two companies, Dromex and Mostostal Warszawa, will undertake the project, which is expected to take 15 months to complete. The plan envisages the construction of two fast roadways and a split level intersection. Work will begin as soon as Gmina Centrum obtains the necessary permission from the Mazowiecki Voivod authorities, possibly as early as this week. (Puls Biznesu, p. 13) M.T.