Tender for Okecie expansion and renovation annulled
The results of the first stage of the tender for the construction of a new
passenger terminal at Warsaw's Okecie Airport have been annulled by the
temporary director of the State Airport Company (PPL), Mieczyslaw Nowak, as
announced on Friday. Two firms that failed to make the short list, Skanska
and Bilfinger & Berger, had earlier filed a protest with the PPL tender
commission, demanding that the tender be invalidated. In late April Nowak
confirmed the selection of German Hochtief AG and French Bouygues Batiment
SA to the second stage of the tender for the design and construction of
Terminal 2, as well as the renovation and modernization of Terminal 1. Last
year seven firms entered the tender, which was supposed to be completed by
June of this year. The new terminal, capable of handling 6.5 million
passengers annually, is planned for completion in early 2005, at a cost
estimated at $300 million. (Rzeczpospolita, May 19-20)