ZAT chemicals not to go ahead with building PVC plant
One of the country's largest chemical plants, Zaklady Azotowe Tarnow (ZAT)
will not go ahead with the construction of a polyvinyl chloride (PVC) plant,
which is one of the basic products of the firm. "The reason for the decision
lies in the failure of a 10-year contract for the supply of vinyl chloride
used for the production of polyvinyl chloride from Oriana of Ukraine which
is part of the Russian concern Lukoil." an informer wishing to remain
anonymous told Puls Biznesu. Vinyl chlorine supplied from Oriana did not
meet appropriate quality requirements and ZAT was forced to buy the material
abroad at a very high price. "So now ZAT is buying the vinyl chloride at a
higher price from the one at which it can sell already produced polyvinyl
chloride." adds the informer. To make the situation worse the plant has
already spent over zl. 40 million on the construction of the facility at the
Tarnow plant which was supposed to be completed in two to two and a half
years, after which ZAT would have been able to produce 100,000 tons of
polyvinyl chloride annually. (Puls Biznesu, p. 5) A.Z.